Hankook - Phase III
Rácalmás

Hankook - Phase III

Client
DAELIM
Year of completion
Industry
Tyre manufacturing
Volume
6M EUR
Scope of work
  • MV, LV systems authorization designing 
  • Siemens NXArir 6kV switchgear installation 
  • Siemens Sivacon 0,4kV distribution panel installations 
  • Cable tray system installation. 
  • MV, LV and instrumentation cables pulling 
  • Complete instrumentation package delivery and installation  
  • Building electrical installation 
  • Fire alarm system installation 
  • Audio-visual and IT systems installation