Project type
Technological solutions
Project profile
Industrial technology
Activities
Prefabrication and installation of pipelines for technology and technology support
Installation of technological and process support equipment
Client
LEGO Hungary
Year of completion
Industry
Plastics Industry - ENB Utility Systems
Volume
5-10 million EUR
Staff
50-60 persons
Scope of work
- Equipment installation and piping erection works in the Energy Building and the related Cooling Tower area.
- Equipment installation:
- Cooling Towers 11 MW
- Chillers 10 MW
- Pumps
- Heat Exchangers
- Equipment for Water Treatments System
- Installation of 2 Hydraulic Tanks – Ø 3,0 m – 8,5 m
- Piping erection including valves.
- Erected diameters: DN15 – DN900
- Fabrication and erection of pipe supports.